What should you test at FAT and SAT, and can it count towards qualification?

By Cormac Falvey, BEng, BSc, PgDip. Published 11 November 2026. Updated 29 November 2026.

Test at FAT whatever can be proven before shipment, and is cheaper to fix at the vendor's works: build quality, documentation, control logic, alarms and functional sequences. Test at SAT whatever depends on the installed site: utility connections, the effects of transport and integration with site systems. FAT and SAT results can count towards qualification if the approach was agreed in advance, the testing was properly controlled, and the function has not been affected by transport or by later changes.

What is the difference between FAT and SAT?

A factory acceptance test takes place at the vendor's site before shipment. Its purpose is to find problems while the vendor's people and tools are on hand. A site acceptance test takes place after installation, and confirms that the equipment still works in its final location and with site utilities.

What should be tested at FAT?

  • Inspection against drawings, and checks of materials and certificates
  • Instrument and component identification against the approved lists
  • Control system functions, sequences and recipes
  • Alarms and interlocks, including what happens when they trip
  • User access levels and data recording, where applicable
  • Review of the documentation package

What should be left to SAT?

  • Installation checks and connection to site utilities
  • Confirmation that nothing was damaged or altered in transport
  • Integration with site systems, such as building management or data historians
  • Functions that FAT could only simulate
  • Close-out of the items left open from FAT

When can vendor testing count towards qualification?

EU GMP Annex 15 allows that, where appropriate and justified, some FAT tests need not be repeated on site at IQ or OQ, if it can be shown that the function is not affected by transport and installation. ASTM E2500 and the ISPE Baseline Guide on Commissioning and Qualification also support using well-controlled vendor and engineering work.

A workable set of conditions is:

  1. The intent to use the results is written into the test plan before the test takes place.
  2. Quality has agreed the approach.
  3. The test protocol is approved, with defined acceptance criteria.
  4. The instruments used are calibrated, with traceable certificates.
  5. The people carrying out and witnessing the test are identified and suitably qualified.
  6. Raw data and results are retained, and deviations are recorded.
  7. The hardware and software tested are the versions delivered, or later changes have been assessed.
  8. A rationale explains why transport and installation do not affect the result.

What does a leverage decision look like?

Illustrative example. The tests and decisions below are invented, and each project must justify its own.

TestPerformed atUsed for qualification?Rationale
Recipe logic and sequenceFATYes, with a software version check at IQLogic is not affected by transport
Alarm responseFAT, sample repeated on sitePartlyField wiring was disturbed for shipping
Temperature control at loadOQPerformed at OQDepends on site utilities
Material certificatesFAT reviewYesDocument evidence does not change

Real Life Example: When It Goes Wrong

On an isolator project, the site made its first attempt at a risk-based approach. A risk assessment was produced, but the execution model was not changed to match it, so the project got the worst of both approaches: heavy verification, with the same tests repeated across several phases. Because the approach was new to the site, the risk assessment took longer than it should have, and it was hard to agree what should be tested where and which vendor and commissioning tests could be leveraged. The result was extra time spent testing on top of the extra time spent assessing. The site was also very risk-averse. That is not a problem in itself, but it needs managing so that everyone is aligned to the new approach. Writing the leverage decisions into the test plan, and agreeing them with Quality before FAT, would have turned the risk assessment into less testing rather than more.

How should FAT punch items be handled?

Record each open item with an owner, a priority and a closure route. Agree which items must be closed before shipment, and which can wait for site. Do not let an open FAT item disappear when the equipment changes location: bring it forward into the SAT list.

What are the common mistakes?

  • Deciding to use FAT results only after the FAT is complete.
  • Accepting a vendor's standard test document without checking it against the URS.
  • Changing software between FAT and delivery without assessing the effect.
  • Sending people to FAT who are not able to judge what they are witnessing.
  • Testing with simulated signals and not recording that the test was simulated.
  • Leaving the documentation review until after shipment.

Frequently asked questions

Is a FAT mandatory?

Not for all equipment. It is decided by the complexity and criticality of the equipment. For complex systems it is usually worthwhile because problems are cheaper to fix before shipment.

Can a SAT replace IQ or OQ?

Parts of it can provide evidence if the same controls are applied and the approach was agreed in advance. A SAT carried out informally is unlikely to support qualification.

Who should attend the FAT?

Usually engineering and automation, and often validation and the process owner. Quality may attend or may review the results, depending on what the results will be used for.

GMP Suite holds FAT and SAT protocols and reports in the same project record as the qualification documents.