How do you build a URS-to-PQ trace matrix that stays current?
By Cormac Falvey, BEng, BSc, PgDip. Published 11 November 2026. Updated 29 November 2026.
A trace matrix stays current when each link is created at the moment the work is done, using identifiers that never change. Link every URS requirement forward to the design response, the risk controls and the test that verifies it, and give every requirement a recorded result or a justified reason for having none. If the matrix is compiled at the end of the project, it is a report on what happened and not a tool for controlling it.
What is a trace matrix meant to prove?
It shows that each requirement was addressed in the design and verified, and that nothing was lost between stages. EU GMP Annex 15 and ISPE GAMP 5 both address the relationship between requirements and the testing that verifies them.
It also works in the other direction. A test with no requirement behind it may be unnecessary, or may reveal a requirement nobody wrote down.
What should the matrix link?
A workable matrix has one row per requirement and links to:
- the requirement identifier, text and criticality
- the design document section that responds to it
- any risk assessment entry that relates to it
- the tests that verify it, at FAT, SAT, IQ, OQ or PQ
- the result of each test, and any related deviation
- a rationale where no test applies
One requirement often needs several tests, and one test can cover several requirements. Build the matrix so that this is allowed.
How do you keep it current during the project?
- Fix the identifiers early. Approve the URS numbering before anything refers to it, and never reuse a number.
- Link at the point of authoring. When a test step is written, record the requirement it verifies at that moment.
- Give it one owner. Many people can add links, but one person should be accountable for completeness.
- Connect it to change control. A change to a requirement should prompt a review of every linked item.
- Review it at stage gates. Check for unlinked requirements before the design is approved, before protocols are approved and before execution closes.
- Take status from results. Show a requirement as verified only when an approved test result supports it.
What does a matrix row look like?
Illustrative example. The identifiers and results below are invented.
| URS | Design | Risk | Tests | Status |
|---|---|---|---|---|
| URS-014: hold 37.0 °C ± 0.5 °C (critical) | FS 2.4 | RA-22 | FAT-12 pass; OQ-07 pass; PQ-03 pending | In progress |
| URS-031: 316L product-contact surfaces (critical) | DS 5.1 | None | IQ-04 pass | Verified |
| URS-052: paint colour to site standard | GA drawing | None | None. Rationale: no GMP impact, checked at commissioning | Closed by rationale |
Real Life Example: When It Goes Wrong
On a purified water generator project, we compiled the RTM after IQ/OQ, just before PQ. Building it showed two gaps. Nothing had verified the minimum city water supply to the system. The SCADA connection had been tested, but the sanitisation data the system sends to SCADA was not part of that test. The URS was part of the problem: it listed the SCADA connection as non-GMP, but the sanitisation data carried over that connection is GMP data. Because neither requirement had been tested, nothing had failed and no deviation was needed. Instead, we wrote and executed a new supplementary IOQ protocol to cover both requirements, and PQ started two weeks late. A check for unlinked requirements before the IOQ protocols were approved would have found both gaps while they could still go into the original protocols. Splitting the SCADA requirement into the connection and the data it carries, each with its own criticality, would have made the GMP data hard to miss.
What about requirements that are not tested?
Not every requirement needs a formal qualification test. Where a requirement is verified by commissioning, by a vendor document, or not at all, record that decision and the reason. An empty cell leaves a reviewer unable to tell whether the omission was a decision or an oversight.
How should a deviation appear?
A failed test should stay visible against its requirement until the deviation is resolved and any retest is complete. Keep the deviation reference in the row, so a reviewer can follow the path from requirement to failure to resolution.
What are the common mistakes?
- Building the matrix just before the final report or an audit.
- Tracing to a protocol as a whole, when the link needs to reach a specific step.
- Retyping requirement text into each document, so that the copies drift apart.
- Marking a requirement as verified when the test has been written but not executed.
- Revising a requirement without checking the tests linked to it.
- Keeping several versions of the matrix with no clear current copy.
Frequently asked questions
Does every requirement need a PQ test?
No. Each requirement should be verified at the stage where it can be shown most directly. Many are verified at IQ or OQ, and PQ focuses on performance under representative conditions.
Can a spreadsheet be used as a trace matrix?
Yes, if it is controlled. The usual difficulties are version control, manual link upkeep and proving that the data has not changed unexpectedly.
Should FAT and SAT appear in the matrix?
Include them where their results are used as verification, so that a reviewer can see which evidence supports each requirement.
Who approves the trace matrix?
This is usually set by the validation plan, and commonly includes validation and quality. Approve it as part of closing out the relevant stage.
GMP Suite builds its trace matrix from the linked project records when the matrix is viewed.