How do you write a URS for GMP equipment?
By Cormac Falvey, BEng, BSc, PgDip. Published 11 November 2026. Updated 29 November 2026.
A user requirements specification (URS) states what the equipment must do to meet process, GMP and site needs. Each requirement must be verifiable. Write every requirement as one numbered statement with a measurable acceptance point, mark which requirements are GMP critical, and approve the document before vendors bid. If a requirement cannot be verified by inspection, test or document review, it is not ready to issue.
What is a URS for, and who relies on it?
The URS is the reference point for everything that follows. Vendors bid against it, designers respond to it, and qualification tests prove it was met. EU GMP Annex 15 treats user requirements as the starting point of the qualification stages.
That means it has several readers with different needs. A vendor needs to know what to price. A designer needs to know what to build. A validation engineer needs something that can be turned into a test with a pass or fail result.
What should a URS contain?
Sections vary by equipment, but most GMP equipment URS documents cover the following:
- Scope and boundaries: what is included, what is excluded, and where the supply ends.
- Process requirements: capacities, ranges, tolerances and operating modes.
- GMP requirements: product-contact materials, cleanability and contamination control.
- Control and data: alarms, recipes, user access and records. Where electronic records are involved, reference 21 CFR Part 11 and EU GMP Annex 11 as they apply, and consider ISPE GAMP 5 for the computerised system approach.
- Site interfaces: utilities, space, access and environmental conditions.
- Documentation: the drawings, certificates, manuals and test records the vendor must supply.
- Constraints: safety, regulatory, schedule or standardisation requirements that limit the solution.
What makes a requirement testable?
Apply these checks to each requirement before issue:
- It says one thing. Split any statement joined by "and" if the parts could pass or fail separately.
- It has a unique identifier that will not change, so later documents can refer to it.
- It uses "shall" for a mandatory requirement, and "should" for a preference, defined once at the front of the document.
- It gives a value, a tolerance and the condition under which it applies.
- It states the need and not a design solution, unless a specific solution is itself required.
- It names the verification method: inspection, test or document review.
- It shows whether it is GMP critical.
What does a good requirement look like?
Illustrative example. The equipment and values below are invented to show the form of a requirement. They are not recommended limits.
| Weak | Testable | Verified by |
|---|---|---|
| The vessel must have good temperature control. | The vessel shall hold product at 37.0 °C ± 0.5 °C across the working volume for 60 minutes. | Test at OQ |
| Materials must be suitable. | Product-contact surfaces shall be 316L stainless steel. | Document review at IQ |
| Changes must be traceable. | Each change to a critical recipe parameter shall record the user, date, time, and old and new values. | Test at OQ |
| It should be easy to clean. | All product-contact surfaces shall be cleanable in place, shown by a coverage test. | Test at OQ |
Real Life Example: When It Goes Wrong
On a previous job, we went into qualification with a URS point stating "The chamber shall maintain a uniform temperature throughout the cycle." On the face of it, that seems like a standard statement in a URS for temperature mapping, but as we discovered it is too vague to qualify. When the vague requirement was discovered on the approved protocol, the Validation team immediately alerted QA to pause execution of the affected test step and agree on numeric acceptance criteria. Under the Change Management procedure, we updated the governing URS, revised the test protocol with objective acceptance criteria, and realigned the Requirements Traceability Matrix (RTM). QA then reviewed and formally approved the updated document package before test execution resumed.
How do you decide which requirements are GMP critical?
Ask whether failing the requirement could affect product quality, patient safety or data integrity. Risk-based approaches such as ASTM E2500 and the ISPE Baseline Guide on Commissioning and Qualification focus verification effort on the aspects that matter most. Marking criticality in the URS lets later risk assessment and testing start from an agreed position.
Avoid marking everything critical. When every requirement carries the same weight, the label no longer helps anyone decide where to spend effort.
Who should approve it, and when?
A typical approval group includes the process owner, engineering, validation and quality. Approve the URS before it goes to vendors. After approval, manage changes through change control, because a late change can affect the bid, the design and the tests.
What are the common mistakes?
- Copying a URS from another project without removing requirements that do not apply.
- Using words that cannot be measured, such as "adequate", "robust" or "user friendly".
- Specifying a vendor's solution, which narrows the bid before the need is defined.
- Leaving out documentation requirements, then asking for them after the order is placed.
- Reusing or renumbering identifiers, which breaks traceability.
- Issuing to vendors before quality and validation have reviewed it.
Frequently asked questions
How long should a URS be?
Long enough to cover what the equipment must do and no longer. Length depends on complexity, and a short URS of testable requirements is more useful than a long one of general statements.
Can a vendor write the URS?
A vendor can help with technical input, but the requirements belong to the user. The regulated company remains responsible for defining what it needs.
Should a URS include design details?
Only where a specific design is itself a requirement, such as a site standard for a component. Otherwise state the need and let the design specification respond to it.
What happens if a requirement changes after approval?
Handle it through change control and assess the effect on bids, design documents, risk assessments and tests that rely on that requirement.
GMP Suite holds URS requirements as individual records that RFPs and protocol steps can link back to.